Inquiry finds ‘gross mismanagement’ in costly VA hospital

DENVER (AP) — Federal investigators say “gross mismanagement,” delays and lax oversight by the Department of Veterans Affairs added hundreds of millions of dollars to the cost of a new Denver-area VA hospital and delayed it by years.

A report from the department’s internal watchdog released Wednesday also said a former senior VA official, Glenn Haggstrom, knew the project was veering toward huge cost overruns but didn’t tell lawmakers that when he testified before Congress in 2013 and 2014.

No phone number could be found for Haggstrom. He retired in 2015.

The report by the VA inspector general repeats some conclusions from earlier investigations but is the most scathing account of the project to date.

The hospital under construction in suburban Denver is expected to cost nearly $1.7 billion, nearly triple the 2014 estimate.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s